ARTICLE - ADJUDICATION

Adjudcation FAQ: the SOP Act in questions and answers

Tan Joo Seng - updated 20 November 2026

The Building and Construction Industry Security of Payment Act 2004 has been improving cash flow in Singapore’s construction industry since 2005, yet many people still do not use it. These are the questions I am asked most often.

Introduction

The Building and Construction Industry Security of Payment Act 2004 (the “SOP Act”) came into operation on 1 April 2005. Its main objective is to improve the cash flow of everyone in the building and construction industry.

Many people still do not know that it exists, or do not understand how it applies, and so do not use it. This article is for them. It is a general overview of how the Act and the adjudication process work in Singapore, in question and answer form.

The article reflects the substantial amendments that took effect on 15 December 2019, and has been refreshed again for November 2026. A key point is that the timelines are strict, so please read the deadlines carefully.

PART 1: THE BASICS

Who is covered under the SOP Act?

The Act covers anyone who has carried out construction work, or supplied related goods or services, in the building and construction industry:

Contractors: main contractors, sub-contractors, sub-sub-contractors and so on.

Suppliers: suppliers of materials used in construction projects.

Consultants: architects, engineers, quantity surveyors and similar professionals.

What type of contracts does the SOP Act apply to?

Three types: construction contracts (to carry out construction work), consultancy contracts (for example the appointment of an architect or engineer) and supply contracts (for goods such as concrete and reinforcement bars).

The contract must be in writing or evidenced in writing, and the work, services or goods must relate to a construction project in Singapore. A partly oral contract can still qualify if the matter in dispute is itself in writing.

What type of contracts are excluded?

The Act does not apply to residential projects that do not need building plan approval under the Building Control Act. A typical example is interior renovation of an apartment with no structural work. It also excludes supply of goods for trading purposes and services provided from Singapore for projects outside Singapore.

How does the SOP Act help to improve cashflow?

It disallows certain contract clauses.

It gives a statutory entitlement to progress payments.

It sets a statutory payment scheme with fixed timelines.

It offers a fast, low-cost process, adjudication, for pursuing progress payments.

Which contract clauses does the SOP Act not allow?

These are void: 

“Pay if paid” and “pay when paid” clauses.

Clauses that try to “contract out” of the Act.

Any provision that is inconsistent with the Act or undermines its intention.

What is the statutory payment scheme?

It is the default scheme that applies to every contract the Act covers. It sets timelines for payment claims, payment responses, payment and adjudication. A contract term that is inconsistent with the scheme is invalid and cannot be enforced.

PART 2: PAYMENT CLAIMS AND RESPONSES

Who can make a payment claim?

Anyone covered by the Act who has done work or supplied goods or services under a written contract. For example:

A main contractor claiming from the project owner.

A nominated or domestic sub-contractor claiming from the main contractor.

A sub-sub-contractor claiming from the sub-contractor.

A consultant claiming from the owner, or from the main contractor in a design-and-build arrangement.

A supplier, plant hirer or related service provider claiming from the party it contracted with.

Must the payment claim meet specific requirements?

Yes. A claim that does not comply with the Act may not be a valid payment claim, and the claimant may then be unable to lodge an adjudication application on it. This is one of the most common reasons I see claims fail.

 

How many claims can be made?

One payment claim for each payment cycle in the contract, and since December 2019, no more than one claim in a calendar month. Unpaid amounts can be rolled into the next claim. Repeat claims are allowed if the claim has not already been adjudicated.

A claim is out of time if it is served more than 30 months after the relevant work, services or supply, so do not leave old claims.

Who should respond to a payment claim?

The party that contracted with the claimant. If the contract says so, an architect, quantity surveyor, engineer or superintending officer can issue the response on that party’s behalf.

What is a payment response?

A written statement of the amount the respondent proposes to pay. It must also comply with the Act. A certificate issued by a project consultant can count as a payment response if it meets those requirements.

If the respondent is withholding any part of the claim, the reasons must be in the payment response. Reasons left out of it will not be considered by the adjudicator, and the Act now disregards late objections unless they could not have been raised earlier.

Why is a payment response necessary?

In every case under a construction contract, whether the respondent intends to pay in full, in part or not at all. If there is no response, the claimant can apply for adjudication.

When must the payment response be given?

By the date in the contract, but no later than 21 days after the payment claim is served. If the contract is silent, within 14 days.

What happens if the payment response is accepted?

The respondent must pay the amount in the response.

When must the claimant be paid?

Construction contracts: by the payment due date in the contract, but no later than 35 days after the due date for the payment response or the date of the tax invoice. If the contract is silent, 14 days.

Pure supply contracts: by the due date in the contract, but no later than 60 days after the payment claim (for example the invoice) is served. If the contract is silent, 30 days.

What happens if the payment response is disputed?

The parties have a 7-day “dispute settlement period” after the due date for the payment response to try to settle. If they cannot, the claimant may apply for adjudication.

PART 3: THE ADJUDICATION PROCESS

What is adjudication?

A statutory dispute resolution process for payment disputes under contracts covered by the Act. An independent adjudicator decides the amount payable on a claim. It is quick and costs far less than Court or arbitration.

Adjudications are administered by the Singapore Mediation Centre (SMC), currently the authorised nominating body, and the SMC appoints the adjudicator from its panel. The decision binds the parties until the dispute is finally decided by a court or tribunal, or settled.

When does the claimant have the right to apply for adjudication?

Construction contracts: 

The claimant accepts the payment response and has given the tax invoice (if needed), but the respondent does not pay the response amount by the due date.

There is no payment response by the due date, and the dispute is not resolved by the end of the dispute settlement period.

The claimant disputes the response amount, and the dispute is not resolved by the end of the dispute settlement period.

Supply contracts: 

The claimant is not paid the claimed amount by the due date.

The claimant disputes a response amount that is lower than the claim and was paid on or before the due date.

 

What is the notice of intention to apply for adjudication?

Before applying, the claimant must tell the respondent in writing that it intends to apply. The notice must meet the Act’s requirements and is lodged with the application.

How does the claimant start adjudication?

By filing an adjudication application with the SMC within the statutory time. The SMC serves a copy on the respondent, notifies the principal (if known) and the owner, and appoints an adjudicator within 7 days of receiving the application.

The deadline is strict. For construction contracts it is generally 7 days after the dispute settlement period ends, and for supply contracts 7 days after the payment due date. The Court of Appeal has confirmed that the day on which the right to apply arises is not counted. A late application is rejected.

When must the respondent reply to the application?

Within 7 days of being served with the application. An adjudication response filed late is disregarded.

What happens after the response is filed?

The adjudicator may hold a conference, issue directions and ask for further documents. The adjudicator then evaluates the claim and issues a determination with reasons. A determination is usually issued within 14 days, and in some cases sooner.

What is the effect of the determination?

The respondent must pay the adjudicated amount within 7 days after the determination is served, or by a later date the adjudicator sets. A claimant that is registered for GST should follow up with a tax invoice, or a credit note for any difference.

 

PART 4: AFTER THE DETERMINATION

How is a determination enforced?

If the respondent does not pay, the claimant has four main options:

Judgment debt. Apply to Court, with an affidavit, for leave to enforce the determination as a judgment.

Direct payment from the principal. The respondent’s principal may, but need not, pay the claimant directly. It can then recover that amount from the respondent.

Lien over goods. The claimant has a lien over goods it supplied that are unfixed and unpaid for.

Suspension. The claimant may suspend the work or supply, after giving the required notice of at least 7 days.

Is the determination final?

No. It binds the parties unless and until the dispute is decided by a court or arbitral tribunal, or settled. The easiest way to think of it is as an interim payment on account. The sum will be accounted for in the final account or in any later arbitration or litigation.

Can a party appeal?

There is no appeal to Court, but the Act gives a review mechanism, open to either side. Broadly, a claimant can apply if the adjudicated amount falls short of the claim by S$100,000 or more, and a respondent can apply if the adjudicated amount exceeds its response amount by S$100,000 or more. The application must be made within 7 days after the determination is served, and the adjudicated amount is paid to the SMC while the review is pending.

Can a party apply to Court to set the determination aside?

Yes, either side can. The Act lists the grounds, and since the 2019 amendments that list is non-exhaustive. Common themes are a breach of natural justice, an adjudicator acting outside the authority given by the Act, and fraud or illegality. A party that applies to set aside must first pay the unpaid adjudicated amount into Court.

The Court can set the determination aside in whole or in part, send all or part of it back to the adjudicator, or correct a clerical mistake or an error from an accidental slip or omission.

AT A GLANCE - TYPICAL TIMELINE

STEP

TIME ALLOWED (CONSTRUCTION CONTRACT)

Payment claim

One per calendar month. Not later than 30 months after the work.

Payment response

By the contract date, up to 21 days after service of the claim. 14 days if the contract is silent.

Dispute settlement period

7 days after the payment response due date.

Adjudication application and notice

Within 7 days after the dispute settlement period.

Appointment of adjudicator

Within 7 days of the application.

Adjudication response

Within 7 days of service of the application.

Determination

Generally, within 14 days after the date for filing of the response. 

Payment of adjudicated amount

Can be within 7 days of the service of the determination. 

Disclaimer. This article gives general information about the Building and Construction Industry Security of Payment Act and is not legal advice. The deadlines are strict and depend on your contract and facts, so please take advice promptly.